RE: Production planning in Dynamics NAV 2009 R2

$
0
0

Hi Ashoka,

You need to look at the 'Dampener (% of Total Capacity) Field' on  The Capacity Constrained Resource Table.

Extract from the help:

"Specifies the tolerance as a percent that you will allow the critical load percent to be exceeded for this work or machine centre.

This tolerance percentage enables the program to schedule a load to a work or machine centre on the last possible day by slightly exceeding the critical load percent."

Regards,

Andrew